The following is a list of proposed Lakes Region projects included in the state’s 10-year transportation plan.

ALTON (PROJECT NO. 40624)

ADDRESS RED LIST BRIDGE CARRYING NH 11 OVER MERRYMEETING RIVER (RED LIST)

$232,492 Preliminary Engineering 2022

$113,080 Right of Way

$1,493,764 Construction 2023

$307,118 Construction 2024

TOTAL $2,421,455

BARNSTEAD (16020)

BRIDGE REPLACEMENT-HANNAH NUTTER ROAD OVER BIG RIVER

$475,964/Construction 2021

TOTAL $1,028,907

BRISTOL (40636)

ROADWAY WIDENING AND SHOULDERS FOR BIKE/PED TRAVEL FROM SCHOOL ST TO WEST OF DANFORTH BROOK RD

$149,376 Preliminary Engineering 2023

$133,578 Right of Way 2023

$2,530,249 Construction 2026

TOTAL $2,978,204

BRISTOL (41579)

BIKE PED IMPROVEMENTS TO LAKE ST.

$270,920 Preliminary Engineering 2027

$13,346 Right of Way 2027

$2,424,931 Construction 2027

TOTAL $2,709,197

CENTER HARBOR - NEW HAMPTON (24579)

Waukewan Road Bridge Rehabilitation over Lake Waukewan Inlet, Redlist Bridge

$904,640 Construction 2021

TOTAL $1,322,640

FRANKLIN (42513)

TRESTLE BRIDGE MILL CITY PARK TRAIL

CONSTRUCT A PEDESTRIAN WALKWAY ON THE EXISTING TRESTLE BRIDGE TO CONNECT TO MILL CITY PARK TRAIL

$25,700 Preliminary Engineering 2021

$630,988 Construction 2024

TOTAL $706,688

GILFORD (40574)

LACONIA MUNICIPAL AIRPORT

PRESERVATION, MODERNIZATION, AND/OR EXPANSION OF AIRPORT FACILITIES; PLANNING STUDIES.

$2,090,266 2021Airport Improvement

$1,393,513 2022 Airport Improvement

$4,072,062 2023Airport Improvement

$1,551,101 2024 Airport Improvement

$1,033,256 2025Airport Improvement

$1,049,074 2026 Airport Improvement

$606,627 2027 Airport Improvement

$692,904 2028 Airport Improvement

$221,170 2029 Airport Improvement

$273,495 2030 Airport Improvement

TOTAL $12,983,469

GILFORD (41502)

ADDRESS RED LIST BRIDGE CARRYING US 3 AND NH 11 OVER US 3 AND NH 11

$113,080 Preliminary Engineering 2021

$1,792,517 Construction 2023

TOTAL $2,125,597

GILFORD (42577)

ADDRESS RED LIST BRIDGE CARRYING NH ROUTE 11 OVER POOR FARM BROOK IN THE TOWN OF GILFORD

$307,118 Preliminary Engineering 2024

$194,734 Preliminary Engineering 2026

$64,911 Right of Way 2026

$2,899,705 Construction 2030

TOTAL $3,466,469

GILMANTON (16234)

BRIDGE REPLACEMENT-CRYSTAL LAKE RD OVER NELSON BROOK

$229,471 Preliminary Engineering 2021

$5,140 Right of Way 2021

$640,457 Construction 2021

$764,068 Construction 2022

TOTAL $1,639,136

GILMANTON (42603)

NH140/NH107

CONSTRUCT PEDESTRIAN ISLANDS AND SIDEWALKS AND IMPROVE CURB

$252,574/Preliminary Engineering 2025

$205,792/Right of Way 2028

$1,449,853Construction 2030

TOTAL $1,908,218

HILL (41661)

BRIDGE REHABILITATION-BUNKER HILL ROAD OVER NEEDLE SHOP

$215,880 Construction 2021

TOTAL                        $515,780

LACONIA (24181)

BRIDGE REMOVAL, CARRYING CENTENARY AVENUE OVER NH RR (RED LIST)

$89,626/Preliminary Engineering 2023

$378,861/Construction 2025

TOTAL $468,487

LACONIA (26706)

BRIDGE REPLACEMENT-ACADEMY ST OVER DURKEE BROOK

(RED LIST)

CategoryStrategy

$179,653 Preliminary Engineering

$10,568 Right of Way

$200,155 Construction 2022 *

$346,988 Construction 2023

TOTAL $737,364

LACONIA (40656)

BRIDGE REPLACEMENT-COURT STREET OVER DURKEE BROOK

$42,271 Right of Way, 2022

$1,147,325 Construction, 2021

TOTAL $2,463,804

LACONIA (41469)

BRIDGE CARRYING US 3 AND NH 11 OVER MILE HILL

$358,503 Preliminary Engineering 2023

$259,646 Preliminary Engineering 2026

$64,911 Right of Way 2026

$3,336,449 Construction 2027

TOTAL $4,019,51

LOUDON - CANTERBURY (29613A)

NH RTE 106 ROADWAY WIDENING (2ND SEGMENT OF PHASE 1) FROM SOUCOOK RD, LOUDON TO AMES RD, CANTERBURY

$5,088,600 Construction 2021

$3,124,000 Previous Funding

TOTAL $8,212,600

MEREDITH (41483)

ADDRESS BRIDGE CARRYING US ROUTE 3 OVER MAPLE STREET AND NHRR

$113,080 Preliminary Engineering 2021

$565,400 Construction 2021

$110,000 Previous Funding

TOTAL $788,480

MOULTONBOROUGH (40639)

SAFETY IMPROVEMENTS FROM JUST WEST OF LAKE SHORE DRIVE (W) TO JUST EAST OF LAKE SHORE DRIVE

$174,369 Preliminary Engineering 2022

$174,369 Right of Way 2022

$1,894,303 Construction 2025

$2,463,042

MOULTONBOROUGH (41580)

COMPLETE STREETS IMPROVEMENTS TO MOULTONBOROUGH CENTRAL VILLAGE.

$179,252 Preliminary Engineering 2023

$94,715 Preliminary Engineering 2025

$12,629 Right of Way 2025

$ 1,312,559 Construction 2027

TOTAL $1,599,155

MOULTONBOROUGH (41581)

SHERIDAN RD AND NH 25 INTERSECTION IMPROVEMENTS

$119,501 Preliminary Engineering 2023

$63,143 Preliminary Engineering 2025

$6,314 Right of Way 2025

$563,860 Construction 2027

TOTAL $752,819

MOULTONBOROUGH (42602)

NH25/REDDING LANE INTERSECTION IMPROVEMENTS

$126,287 Preliminary Engineering 2025

$66,729 Right of Way 2027

$564,145 Construction 2029

TOTAL $757,161

NEW HAMPTON (25365)

REMOVAL OF BRIDGE CARRYING SMITH CROSSING OVER NH RAILROAD (RED LIST)

$28,270 Preliminary Engineering 2021

$315,717 Construction 2025

TOTAL $426,487

PLYMOUTH (41583)

RECONSTRUCTION & INTERSECTION IMPROVEMENTS TO HIGHLAND STREET

$94,474 Preliminary Engineering 2027

$13,346 Right of Way 2027

$1,369,870 Construction 2027

TOTAL $1,477,689

RUMNEY (27162)

BRIDGE REPLACEMENT-BUFFALO RD OVER BROOK

$84,543 Preliminary Engineering 2023

$5,284 Right of Way 2023

$192,863 Construction

TOTAL $475,553

SANBORNTON-NEW HAMPTON (41705)

PAINTING I-93 BRIDGES BETWEEN SANBORNTON AND NEW HAMPTON

$ 2,452,796 Construction 2022

TOTAL $2,492,396

TILTON (42600)

INTERSECTION SAFETY IMPROVEMENTS (ROUNDABOUT)

$614,236 Preliminary Engineering 2024

$333,645 Right of Way 2027

1,496,544 Construction 2029

TOTAL $3,063,548

WOLFEBORO (29615)

IMPROVEMENTS FROM NH 109 TO ALTON TOWN LINE

$668,416 Right of Way 2022

$9,012,766 Construction 2024

TOTAL $10,586,749

LINK TO THE 10-YEAR PLAN: www.nh.gov/dot/org/projectdevelopment/planning/typ/documents/8.12TYPBook.pdf

Recommended for you

(0) comments

Welcome to the discussion.

Keep it Clean. Please avoid obscene, vulgar, lewd, racist or sexually-oriented language.
PLEASE TURN OFF YOUR CAPS LOCK.
Don't Threaten. Threats of harming another person will not be tolerated.
Be Truthful. Don't knowingly lie about anyone or anything.
Be Nice. No racism, sexism or any sort of -ism that is degrading to another person.
Be Proactive. Use the 'Report' link on each comment to let us know of abusive posts.
Share with Us. We'd love to hear eyewitness accounts, the history behind an article.